Project Schedule

*Please note – all dates are estimated and subject to change, unless noted as "CONFIRMED".  Please stay tuned for public notices.

 

December 2017 – Article 10 – File Final Public Involvement Program Plan with NYS DPS
 

February 20th, 2018 | 3:00 PM – 5:30 PM, and 6:30 PM – 9 :00 PM | Town Hall, 18 Russell Avenue, Ravena, NY 12143 - CONFIRMED
 

July 2018 – Article 10 – File Preliminary Scoping Statement with NYS DPS – 21-day public comment period - Complete
 

July 2018 – Article 10 – Intervenor Funding Made Available to Municipal and Local Parties - Complete
 

July 2018 – Article 10 – Nominations Considered for Local Members of Siting Board
 

December 2018 – NYISO Interconnection Studies Complete

 

November 2018 – Article 10 – Full Application Submitted to NYS DPS

 

November 2018 – Public Open House Informational Meetings – Coeymans, New York  

 

January 2019 – Article 10 – Full Application Deemed Complete by NYS DPS
 

January 2019 – December 2019 – Article 10 – Adjudicatory Process – Public Hearings
 

December 2019 – Article 10 – Siting Board Decision
 

December 2019 – Commence project procurement and construction
 

3rd Quarter 2020 – Commence Facility Operation

© 2018 Hecate Energy